Capital Projects

Per LOWA Admin resolution 2015-6 this web page was designed to help keep members informed about projects funded by the New Asset and Improvement Reserve (NAIR).  The purpose of the NAIR is to set aside monies to acquire new assets or to improve existing assets that are not included in the formal Reserve Study Analysis, or reflected in the accounting records of LOWA. These monies can also be used to cover the cost of significant additions to existing buildings.  

Other capital projects, such as those funded by one of the other the three funds,  Repair & Replacement Reserve (R&R), Contingency Reserve (CR), and New Construction & Renovation Fee Reserve (NCRF), may be included on this page if the LOWA Board of Directors and / or the GM deem it appropriate.

Clubhouse Area Recreation Complex Project


 The Clubhouse Area Recreation Complex Project (CARC) is a major capital project that is designed to reconstruct, renovate, update the amenities in the area of the Clubhouse. The CARC project gives our community 25 ADA-compliant parking spaces for the Clubhouse, beach, fitness center and pool. Our old beach bathrooms will be replaced and moved closer to the beach. The fifty-year old bathhouse/fitness center building will be replaced with new infrastructure that will better meet the needs of our members. The swimming pool will be replaced with a/multipurpose pool that will meet the needs of all ages, from toddlers to seniors, as well as the needs of our physically challenged members. The old snack bar for the pool will be replaced by a new snack bar serving all members using the Clubhouse beach area, not just pool users. A new basketball court will be built for our youth to replace the old court.

Clubhouse Area Recreation Complex
Project Update
As of December 5, 2018

Project Cost Estimate (Budget):  $5,086,193
 
Current Funding:   

  • $458,422 – Cash allocated by Board
  • $818,000 – Year 1 ($191/lot) billed in Regular Assessment
  • Up to $5 Million Mutual of Omaha Bank loan in place June 20.

RRMM Lukmire Architects Cost Comparison
Downey Scott Cost Estimate- February 22, 2018
Wack General Contracting Master Schedule

Project Progress

Design: 100 percent complete
Bidding: Complete.  Board awarded construction contract to Wack General Contractor (Thos. J. Wack Company) May 16. Contract executed June 8. 
Permitting: Complete 
Construction: Schedule June 2018-June 2019
Completed

  • Began installing CMU footing on pool house (New)
  • Under slab pool piping installed.
  • Placement #57 stone compacted on pool floor. (New)
  • Parking lot grading finalized and prepped for asphalt contractor (New)
  • Total to date: $757,755.51
 
Upcoming
  • Complete rebar install and grounding/bonding in pool shell (New)
  • Plumbing rough in for under slab plumbing in the Fitness Building(New)
  • Complete parking lot asphalt base (New)
Communication:
  • April 30 Information Session was a success with 109 members participating

Project Photo Archive



Wack General Contracting Reports


CARC Project Information Links

Click on the links below for more information about the project:

Lake Currents Articles Regarding CARC

Wack General Contracting Master Schedule

Project Graphics & Renderings