Update - February 21, 2025

2/21/2025

Progress Update: Patrick Henry Court Drainage Improvement Project: 75% COMPLETE, estimated completion April 2025.
  • The excavation for the stormwater basin at LOWA Lots 707 and 709 on Yorktown Blvd. was completed during the week of 2/19.
  • Steady Construction plans to complete the pipeline installation between Hollyfield Park and Patrick Henry Court during the week of 2/24, weather permitting.
  • To address excess water in the construction zones caused by recent weather, the contractor is actively managing water mitigation efforts.
  • The contractor will prepare the pipeline construction area on Patrick Henry Court during the week of 3/3, weather permitting. Jersey Wall barriers will be placed in the work zones on Patrick Henry Court and will be moved as the pipeline work progresses. Members will receive advance notification before the contractor places the barriers on Patrick Henry Court.
  • Weather permitting, the contractor will begin construction of the pipeline connecting the Yorktown water detention pond to the Patrick Henry Court pipeline during the week of 3/10.
  • The pipeline work will cross Yorktown Blvd., requiring road closure to through traffic in the 600/700 block between the intersections of Hollyfield Park Drive and Fairfax Lane. Members will be notified before the road closure. The Yorktown Blvd. road closure is scheduled to be in effect from March 10 to March 21. Only local traffic will be allowed to access this section of Yorktown Blvd.
  • Hollyfield Park playground is closed and will remain closed until the project is completed.
  • The pickleball and tennis courts remain open