UPDATE October 1, 2025

10/1/2025

Progress Update: Patrick Henry Court Drainage Improvement Project: 98% COMPLETE, estimated completion October 2025. 

  • Paving is delayed and will not be completed until after the Patrick Henry Court pipeline construction is complete. 

  • Work on the drainage pipeline crossovers along Patrick Henry Court is underway but cannot be completed until RSA relocates and upsizes a water main that conflicts with this portion of the project. RSA recently determined that this water main must be upsized, requiring a bidding process and seven days’ notice once a contractor is selected. This change will delay completion of the drainage pipeline crossovers on Patrick Henry Court.  

  • Hollyfield Water Detention Facility-final grading, setting a drainage structure, and installment of riprap is in progress. 

  • Yorktown Blvd. Water Detention Facility- riprap installation in progress and grading is complete. 

  • After the Patrick Henry Court pipeline crossovers are completed, final cleanup of project sites and demobilization of contractor equipment will begin.  

  • Yorktown Boulevard from Patrick Henry Court to Fairfax Lane is open to traffic. 

  • Erosion and sediment control fencing will remain in place until new grass is established. 

  • The Hollyfield Park playground remains closed, with plans to reopen in mid-October. 

  • The pickleball and tennis courts and the ball field are open.