1/31/2025
Patrick Henry Court Drainage Improvement Project Update 1/31:
- Tree cutting and removal is complete at the two LOWA Lots (707 & 709 Yorktown Blvd) for the stormwater basin location.
- Excavation at the two LOWA Lots (707 & 709 Yorktown Blvd) for the stormwater basin started on 1/30. Work is expected to be completed by 2/10, weather permitting.
- Tree removal on Patrick Henry Court and Yorktown Blvd. is complete.
- Hollyfield water detention facility digging is complete and the contractor is removing excess material from the basin.
- Pipeline construction by the contractor (Steady Construction) on Patrick Henry Court will begin 2/10.
CONSTRUCTION ZONE ALERT:
To prepare for the pipeline work on Patrick Henry Court,
Jersey Wall barriers will be set on Patrick Henry Court next week, between 2/5-2/7. Be aware that the area where the Jersey Walls are located will limit the roadway to a single lane.
Please proceed with caution on Patrick Henry Court.
- The drainage connection between Hollyfield and Patrick Henry Court is under construction by the contractor.
- Installation of the micro pool within the water detention facility in Hollyfield Park has been rescheduled to occur after the stormwater basin on Yorktown Blvd. is complete.
- Hollyfield Park playground is closed and will remain closed until the project is completed.
Pickleball courts and tennis courts remain open.