UPDATE December 15, 2025

12/15/2025

Hollyfield Park Work Update:
  • The horseshoe pit installation is completed.
  • Tree replacement planting is in process along the perimeter of the project area of Hollyfield Park. Two shade trees in the parking area have been planted.
  • Water Detention Facility: The micro pool in the water detention facility has a drainage structure that is scheduled to be capped by the contractor (Steady Construction) and a removable bollard to be installed by the contractor at the parking lot side access. 
 
Patrick Henry Court Drainage Pipeline Work Update:
  • RSA has completed all utility conflict work on Patrick Henry Court.
  • Steady Construction completed ditch and manhole structure work at the intersection of Patrick Henry Court and Yorktown Blvd.
  • The contractor completed the two drainage pipeline crossings on Patrick Henry Court.
  • Ditch grading and drainage structure caps are in process of being completed on Patrick Henry Court, weather permitting.
 
Yorktown Blvd. Water Detention Facility Work Update:
  • A gravel entrance area, vegetated spillway, and a removable bollard at the driveway remain to be finished.
Steady Construction is in Final Steps of the project:
  • Crews will begin final site cleanup and demobilization of construction equipment.
  • Erosion and sediment control fencing will remain in place until new grass is fully established.
Final Steps: Scheduled for Spring 2026
  • Paving on Yorktown Blvd. and tar-and-chip work on Patrick Henry Court will be completed in the Spring 2026 due to temperature requirements.
  • Tar and chip will be applied to all Hollyfield Park parking areas in the Spring 2026 due to temperature requirements.