8/15/2025
Patrick Henry Court Drainage Project Update 8/15:
Utility Relocation has been completed.
The RSA contractor completed the water main relocation this week.
🚧 Yorktown Blvd. Construction (Aug. 18-22):
Steady Construction continues work on the manhole structure and pipeline along Yorktown Blvd. As the project is still in progress, the road cannot be reopened for through traffic as originally planned. Completion of the pipeline and road is now expected by mid-week next week.
🚧 Upcoming Work at Patrick Henry Ct. Intersection:
The pipeline crossover project at the intersection of Patrick Henry Court and Yorktown Blvd. has been rescheduled to begin the week of August 25. During this time, expect temporary lane closures and occasional short-term full closures.
Residents on Patrick Henry Court will receive direct notification prior to the start of work that week.
🌳 Hollyfield Park Updates:
- Remaining work in the park and along Patrick Henry toward Yorktown Blvd. is scheduled for completion during the week of August 18–22, along with cleanup of the project site.
- Grading and seeding work is ongoing at the water detention facility.
- Erosion and sediment control fencing will remain in place until new grass is established.
- The Hollyfield Park playground remains closed, with plans to reopen in early September.
🚫 ROAD CLOSURE NOTICE:
Yorktown Blvd. remains closed to thru traffic between the intersection of Patrick Henry Ct. and Fairfax Lane.
LOWA will notify members as soon as the road reopens.