4/23/2025
Progress Update April 23, 2025:
- RSA will has identified a contractor to complete the water main utility conflict. Work is estimated to begin in 2 weeks. The utility work is estimated to be completed in one-two days.
- Yorktown Boulevard (from Patrick Henry Court to Fairfax Lane) will remain closed until further notice.
- Patrick Henry Court/Yorktown Blvd. intersection closure has been delayed. Work is expected to begin on the pipeline crossing at Patrick Henry Court in 7 days. The Contractor will use a metal plate over the pipeline construction area in the road to allow local traffic to access Patrick Henry Court during the construction.
- Steady Construction crews are working on the drainage pipeline on Patrick Henry Court moving toward the pipeline connection at Hollyfield Park. Progress has been delayed due to bed rock encounters.
The pickleball and tennis courts and the ball field are open.
Hollyfield Park playground is closed and will remain closed until the project is completed.
ROAD CLOSURE REMINDER:
Yorktown Blvd. is closed to thru traffic
from the intersection of
Patrick Henry Court and Fairfax Lane
until further notice.
Only local traffic will be allowed to access this section of
Yorktown Blvd.