UPDATE April 2, 2025

4/2/2025

Progress Update April 2, 2025:

Utility Conflict: Steady Construction has discovered a 12-inch water main conflict at the planned manhole structure on Yorktown Boulevard.

 

  • RSA will resolve the issue, with work expected to be completed within 2-3 weeks after the bidding process.
  • This must be addressed before drainage pipeline work crossing Yorktown Blvd. can proceed.

Road Closures:

  • Yorktown Boulevard (from Patrick Henry Court to Fairfax Lane) will remain closed until further notice.
  • Patrick Henry Court/Yorktown Blvd. Intersection Closure: Beginning April 2 through April 4. (Work is estimated to take 2-3 days.) The Contractor will use a metal plate over the pipeline construction area in the road to allow local traffic to access Patrick Henry Court.

Construction Update:

  • Crews are working on the drainage pipeline from Hollyfield Park water detention basin moving toward the connection at Patrick Henry Court.
  • Construction of the pipeline along the roadside of Yorktown Boulevard is underway and has reached the intersection of Patrick Henry Court and Yorktown Blvd. 

Reopening of Facilities:

  • The back parking lot near the ball field and pickleball courts has reopened.
  • The ball field at Hollyfield Park is open for use.
  • The pickleball and tennis courts remain open.

Hollyfield Park playground is closed and will remain closed until the project is completed.

 

 

ROAD CLOSURE REMINDER:

Yorktown Blvd. will be closed to thru traffic

from the intersection of

Patrick Henry Court and Fairfax Lane

until further notice.

 

Only local traffic will be allowed to access this section of

Yorktown Blvd.

 

Please use alternate routes avoiding this area of Yorktown Blvd

if possible during the scheduled Road Closure.