3/7/2025
Progress Update March 7, 2025:
- BZ Excavating, the project contractor, completed work on the subbase which was followed by the application of an asphalt base coat in the relocated Member Lane.
- Boring electrical wiring for the new member lane island and guard shack is scheduled to begin the week of 3/10.
- Moving the Member Lane security gate will be scheduled after boring electrical work is complete.
- Concrete curb work was completed for the lower island curb structure.