3/3/2025
Progress Report Update March 3, 2025:
- BZ Excavating, the project contractor, resumed work on the relocated member lane during the week of 2/24. The team completed work on the subbase which was followed by the application of an asphalt base coat.
- The contractor (BZ Excavating) will begin boring electrical wiring for the new member lane island and guard hut the week of 3/3.
- Concrete work will begin Monday 3/3 for the Main Gate project which will close the Member Lane temporarily on Monday, 3/3 from noon until 3:30 PM. Traffic will be moved through the visitor lane during that scheduled time.