UPDATE March 19, 2025

3/19/2025

Progress Update March 19, 2025:

  • BZ Excavating, the project contractor, completed boring electrical wiring for the new member lane island, guard hut, and streetlights on 3/14.
  • Concrete work is scheduled for Wednesday, March 19 for the new member lane island.
  • Concrete work for the Main Gate project today, Wednesday, March 19 will cause the Member Lane to be closed at the Main Gate Entrance temporarily. All member and non-member traffic will be directed through the Visitor Lane.

IMPORTANT: WEDNESDAY, MARCH 19
the Main Gate Entrance will have ONLY ONE Lane to enter from Noon - 5:00 PM.
 
  • Moving the member lane security gate will be scheduled after the concrete work is completed for the new member lane island the week of 4/7.