Demolition of the old facilities will begin the week of July 23rd and will be scheduled during the hours of 7 AM - 3:30 PM.
Completed Items:
  • The propane tank removal
  • Safety sign have been installed along the perimeter of the fence
  • Both trailers have been delivered and placed
  • Electrical meters and light poles have been disconnected
  • Comcast has surveyed the site in order to hookup internet to the trailers
  • DEQ permit has been received and submitted to Orange County
  • Land disturbance has been approved
  • Trailer zoning permits have been approved
Next Week’s Items:  
  • Start Erosion & Sediment Control
  • Re-stake the site. (only missing items)
  • Schedule Erosion & Sediment inspection
  • Cut in the roads for the construction
  • Begin demolition