3/1/2019

Week In Review For 2-25-2019
      For the last week of February, you couldn’t have asked for better weather. Having plenty of sunshine, and mild temperatures helped make this week a very productive one. 
      B.G. Crane finished up Tuesday with the placement of all remaining metal roof decking, and support angels and clips. We had the third party inspector (DEA) on site Tuesday taking care of the final steel inspection of all remaining items, and everything passed without any deficiencies. 
    
  Miller Interiors crew mobilized Monday and began placement of the 3/4 sheathing over the metal roof decking of the Fitness Center Building which had been inspected and released last week. By Tuesday this side was covered, and they started on the roof of the Pool House. The 3/4 sheathing will be used as a nailer for placement of the shingles. Miller Interiors also began installing the 7/8’s metal Hat Channel on the Pool House exterior wall just above the finish grade of the brick veneer, and cast stone. On Thursday part of the crew fell back and began placement of the exterior hollow metal door frames. Miller will be working this weekend, finishing up the roof sheathing, and begin the layout, and framing of the interior walls of the Fitness Center. 
   
  Ramsey Masonry continued placement of remaining interior CMU walls of the Pool House Restroom, and placement of the exterior brick veneer on the Pool House. 
   
  Creative Conservation finished up Wednesday with the application of the water proof air barrier on the Fitness Center Building. They will be back in a few weeks to apply the spray foam to the under side of the roof decking once all framing, placement of duct, and hanger wire has been installed.  
   
  Unlimited Plumbing began the routing of above ceiling pipe in the Fitness Center, and continued working with the mason installing remaining plumbing pipe as wall were laid. 
   
  Tommy Wallace Electrical continued to pop in and out this week finishing up placement of remaining electrical conduit and boxes where needed within the CMU walls. 
   
  This concludes the list of activities that took place this week. Hope everyone has a great weekend. 

Week In Preview For 3-4-2019
     This weeks activities will consist of the following, Ramsey Masonry will continue placement of the brick veneer of both buildings. They will complete the placement of remaining CMU interior walls of both buildings.
     Miller Interiors will continue placement of exterior wall hat channel on both buildings, begin the framing of the roof cupola, and continue framing of the interior walls of the Fitness Center.
     Unlimited Plumbing will continue routing of above ceiling piping, and fall back and begin plumbing roughing in of framed metal stud walls.
Tommy Wallace Electrical will begin Electrical rough in of metal stud walls, and above ceiling rough in work.
      I.C.E will mobilize Tuesday and begin placement of all above ceiling duct work.
Wilsey Roofing will mobilize mid week to apply the ice, and water shield over the roof sheathing.
      R.J. Biringer will be here to finish concrete placement of remaining building column block outs, and housekeeping pads.
      Sounds to be expected will continue to be those of equipment moving about the site, and back up alarms.
      Traffic in the area will be light with occasional deliveries from vendors being made, and a few contractors demobilizing remaining items.