Skip to content
Member Login
Logout
Home
Latest News
Life at the Lake
Play & Explore
Events & Connections
The Heart of Lake Life
Events & Meetings
About
Local Info
Local Links
Clubs
Community Organization & Resources
Latest News
Dam Emergency Action Plans
Employment Opportunities
LOWA Amenity Map
Administration
Board of Directors
Forms
Governing Documents
Requests for Proposals
Golf
Subscribe to Golf Email
Amenities
Restaurants
Clubhouse
Fareways Cafe
Community Center
Equestrian Center
Fitness Center
LOWA Communications
Lakes & Marinas
Pickleball & Tennis
Swimming Pools
SOGGY DOGGIE
Parks and Campground
Boat Test & Registration
Calendar & Events
LOWA FALL FESTIVAL
LOWA Independence Day Celebration
LOWA Parade Recognitions
Holiday Home Decorating Contest
Holiday Home Decorating Contest WInners
Security
TEK Control LOG-IN
Contact Us
Contact Our Team
Smart Web
Real Estate
Page content
Update-March 3, 2025
3/3/2025
Progress Update March 3, 2025:
The contractor will prepare the pipeline construction area on Patrick Henry Court during the week of 3/3, weather permitting. Jersey Wall barriers will be placed in the work zones on Patrick Henry Court and will be moved as the pipeline work progresses.
Weather permitting, the contractor will begin construction of the pipeline connecting the Yorktown water detention pond to the Patrick Henry Court pipeline during the week of 3/10.
The pipeline work will cross Yorktown Blvd., requiring
road closure to through traffic
in the 700 block
between the intersections of Hollyfield Park Drive and Fairfax Lane.
Members will be notified before the road closure.
The Yorktown Blvd. road closure is scheduled to be in effect from March 10 to March 21. Only local traffic will be allowed to access this section of Yorktown Blvd.
Hollyfield Park playground is closed and will remain closed until the project is completed.
The pickleball and tennis courts remain open