Patrick Henry Court Drainage Project Update 9/19:

Paving is delayed and will not be completed until after the Patrick Henry Court pipeline construction is complete.
Work on the drainage pipeline crossovers along Patrick Henry Court is underway but cannot be completed until RSA relocates and upsizes a water main that conflicts with this portion of the project. RSA recently determined that this water main must be upsized, requiring a bidding process and seven days’ notice once a contractor is selected. This change will delay completion of the drainage pipeline crossovers on Patrick Henry Court by approximately 3–4 weeks. 
Hollyfield Water Detention Facility-final grading, setting a drainage structure, and installment of riprap is in progress.
Yorktown Blvd. Water Detention Facility- riprap installation in progress and grading is complete.
After the Patrick Henry Court pipeline crossovers are completed, final cleanup of project sites and demobilization of contractor equipment will begin. 
Yorktown Boulevard from Patrick Henry Court to Fairfax Lane is open to traffic.
Erosion and sediment control fencing will remain in place until new grass is established.
The Hollyfield Park playground remains closed, with plans to reopen in early October.
The pickleball and tennis courts and the ball field are open.