1/31/2025
Progress Update: Main Gate Traffic Congestion Relief Project 1/31:
- The remediation plan for substrate findings has been completed for the relocated member lane.Contractor (BZ Excavating) will achieve VDOT 100% compaction requirement in the relocated member lane early next week, 2/3-2/5, weather permitting.
- The relocated member lane is scheduled for base asphalt after compaction is achieved the week of 2/3, contingent on paving subcontractor availability.
- Boring for electrical wiring of relocated member lane island and guard shack to begin during the week of 2/3.