LOW Paving Projects

10/12/2021

LOWA Paving Update
10/12/2021
Lakeview Parkway Paving Main Gate to Clubhouse Parking Lot Entrance
 
All work schedules are weather permitting and may be delayed a day or two if there is rain.
  • Chemung Contracting is finalizing the paving of the stretch of Lakeview Parkway located between the main gate and the first entrance of the Clubhouse parking lot. This part of the project will be concluded by today, Tuesday, October 12.
  • Traffic entering the main gate may only turn left or go straight and detour through the Clubhouse parking lot to exit out on to Lakeview Parkway at the dam side exit.
  • Members seeking to access the Holcomb building should park at the Clubhouse parking lot and walk over. Call 540-972-2237 if you need assistance.

Lakeview Parkway Paving Liberty Blvd.
to Constitution Blvd.

 
All work schedules are weather permitting and may be delayed a day or two if there is rain.
  • Chemung Contracting will be paving the stretch of Lakeview Parkway that runs from just before Liberty Blvd. up to Constitution Blvd.
  • Traffic will be directed to pass through one lane at a time or members may detour around the work via Yorktown Blvd.
  • Work will begin Wednesday, October, 13 and will be concluded on or before Thursday, October 14.
  • Contractors will be on site daily from 7:00 AM until around dusk.

Woods Center / Maintenance Parking Lot Paving
 
All work schedules are weather permitting and may be delayed a day or two if there is rain.
  • Chemung Contracting will be paving the Woods Center / Maintenance parking lot and the adjacent mail station.
  • Work to excavate areas of the parking lot and install sidewalks will begin Monday, October 18 and will be concluded on or before Thursday, October 21.
  • Contractors will be on site daily from 7:00 AM until around dusk.
  • Parking may be limited during the excavation and sidewalk installation.

  • Paving work will be begin on Tuesday, October 26 and will be concluded on or before Wednesday, October 27
    • Parking will be limited and may be unmarked.
    • Members should try and car pool when visiting any of the adjacent amenities until paving has concluded.
    • Please refrain from parking on the road.
  •  Affected amenities include:
    • Woods Center
    • Fareways Cafe
    • Golf Course & Pro Shop
    • ECC Office
    • Maintenance Building

Mail Station Paving at Spotswood, Harpers Ferry, and Fairway Drive (Woods Center)
All work schedules are weather permitting and may be delayed a day or two if there is rain.
  • Chemung Contracting will be paving the mail stations on the following dates:
    • Spotswood- Thursday, October 21
    • Harpers Ferry- Friday, October 22
    • Fairway Drive- Monday, October 25
  • Contractors will be on site from 7AM  until around dusk.
  • Members and mail carriers will have access to the mail station at all times.