7/27/2018
Clubhouse Area Recreation Complex
Project Update July 27, 2018
Reported by Wack General Contracting
Wack Project Management Timeline
Completed
-Ground Breaking Ceremony
-The propane tank has been removed
- Abatement has been completed
-The site crew has been on the site to go over the Erosion & Sediment and construction entrances.
- Staking for permanent entrance/access to the RSA pump station
-All trees to be removed have been flagged.
Scheduled for the week of 7/30 -8/03
-The temporary fence is being moved and will now be closer to Sailboat Beach, impeding a portion of the walking trail, members can still walk around the fence.
-Water/sewer will be disconnected from the pool bathrooms.
- Erosion & Sediment Controls installation begins.
- The tree protection installation begins.
- The (2) construction entrances installation begins.
- Demolition mobilization towards the end of the week.
Demolition rescheduled to begin August 13